5 March 2009, 00:00
Topics identified for deeper cooperation included future common education and training programs for operational staff. Also, Vattenfall Europe Transmission GmbH presented for further consideration the participation of PSE Operator S.A. in the planned control area co-operation for control power of VE Transmission, E.ON Netz and EnBW TNG.
The activity progress in the areas of Investment, Development Planning, Operations and Communication made during the past year were reviewed and assessed. Furthermore, the TSOs agreed to install phase-shifter transformers in the Krajnik and MikuĊowa substations in connection with voltage level switch to 400 kV in Krajnik-Vierraden interconnection to improve the co-operation of both power systems. This will also allow power exchange on the market.
The construction of the 3rd interconnection line on the Polish - German border was another key point of the meeting. A precise schedule of this project will soon be agreed by both parties including organizational and programmatic matters.