Poland-Lithuania Power Interconnection - Formal beginning of the construction works on the part of Lithuania

6 May 2014, 00:00

Poland-Lithuania Power Interconnection - Formal beginning of the construction works on the part of Lithuania
On 5 May 2014, in Lithuanian Alytus, the ceremony was held on the occasion of beginning the construction works on the power interconnection between Alytus and the border of the Republic of Poland. The ceremony was attended by Dalia Grybauskaite – President of Lithuania and Jaroslav Neverovič – Minister of Energy of Lithuania, Deputy Voivode of Podlasie – Wojciech Dzierzgowski, Henryk Majchrzak – President of PSE and Cezary Szwed - Member of the Board of PSE.

Currently, the Lithuanian transmission system is not connected to the European system. Thanks to this Project, the European market and the electricity markets of the Baltic States (Lithuania, Latvia and Estonia) will be interconnected with continental Europe, which will allow to close the so-called Baltic Ring. The Poland-Lithuania interconnection will also improve the energy security of Poland and Lithuania and will make the export and import of energy possible.

As part of the interconnection, more than fifty kilometers (51 km) of the overhead power line will be constructed in Lithuania, from the border of the Republic of Poland to the Alytus substation. In the Alytus substation, a relevant B-T-B 500MW unit will be installed to enable the interconnection of the Polish and Lithuanian transmission systems. In addition, appropriate modernisation of the entire 330/110/10 Alytus substation is carried out. The construction works in Lithuania are to be completed by the end of 2015.

On the Polish partof  the Project, the Poland-Lithuania power bridge covers not only building the line from the Ełk Bis substation to the border of the Republic of Poland, which will be connected with the Lithuanian Alytus substation. At the same time, the power lines and substations in the regions: Mazowieckie, Podlaskie and Warmińsko-Mazurskie are being constructed and modernised. In total, under the Project 11 large investments in the network infrastructure are implemented, which will enhance the reliability of power supply to Central and North-Eastern Poland and thus the possibility of the economic development of the region.:

  • 4 400 kV power lines of with a total length of about 400 km. The 400 kV line Ostrołęka-Łomża-Narew with a total length of about 118 km is in the final phase of implementation. The construction of this line is planned to be completed at the end of the 4th quarter of 2014.

    Other investments regarding power lines are planned to be completed by the end of 2015.

  • 7 substations – 5 new and 2 are being modernised.

    The Ołtarzew substation has already been constructed and put into operation. On 22 April, the opening ceremony for that substation was held, with participation of Janusz Piechociński – Deputy Prime Minister and Minister of Economy.

    Regarding to the remaining substations, the advanced construction works are carried out. The construction of the Łomża substation and modernisation of the Narew substation are planned to be completed in the 4th quarter of 2014. Other substations’ investments are planned to be completed in the period 1st-2nd quarter of 2015.

The total value of all investments under the Poland-Lithuania Power Interconnection is about PLN 1.8 billion.

The Poland-Lithuania Power Interconnection Project is co-financed from the EU funds within the framework of the Operational Programme Infrastructure and Environment 2007-2013. This Project matches the objectives of the Programme’s Priority X, through the implementation of investment tasks which aim at increasing the energy security of the country, by means of the development of the power transmission system.