Information on changes of specification of EDI standards (WIRE Standards) resulting from the implementation of the new cross border scheduling principles

23 April 2010, 00:00

Information on changes of specification of EDI standards (WIRE Standards) resulting from the implementation of the new cross border scheduling principles
Due to the implementation of the new cross border scheduling principles planned for 1 September 2010, PSE Operator will update the specification of EDI standards (WIRE Standards) according to the requirements of FBA method. Therefore it will be necessary to ensure that the WIRE/UR systems of the Scheduling Coordinators (Operatorzy Rynku - OR) are consistent with the new WIRE Standards.

The acceptance tests will be conducted using the test environments of the Scheduling Coordinators and TSO. It is also possible to conduct the acceptance tests of WIRE/UR system by the software vendors. The Scheduling Coordinators who have WIRE/UR systems certified for compliance with the WIRE Standards by software vendors will be exempt from having to hold acceptance tests.

The table below depicts the preliminary time schedule of the implementation project.

The preliminary time schedule of the changes of WIRE Standards
Activity
Responsible
Planned date
1
Update of the Grid Code (IRiESP).
TSO
Immediately after approval of the updated Auction Rules 2010 by 5 TSOs and NRAs.
2
Publication of the draft of WIRE Technical Standards 11.0.
TSO
21.05.2010
3
Consultation of the draft of WIRE Technical Standards 11.0.
Software
vendors /
Scheduling Coordinators
07.06.2010
4
Publication of WIRE Technical Standards 11.0.
TSO
15.06.2010
5
Implementation of the changes resulting from WIRE Technical Standards 11.0 on TSO side.
TSO
do 12.07.2010
6
Testing period of WIRE/UR systems.
Scheduling Coordinators /
TSO /
Software
vendors
od 12.07.2010
do 20.08.2010
7
End of adaptation process of Scheduling Coordinators’ information systems to electronic data exchange according to WIRE Technical Standards 11.0.
Scheduling Coordinators
31.08.2010

The detailed time schedule of the implementation measures related to the changes in WIRE Standards will be described in the Procedure for amending WIRE Standards (Procedura wprowadzania zmian w Standardach technicznych systemu WIRE), which will be published together with new technical Standards of WIRE system 11.0.

The Market Participants who are not equipped with WIRE system should follow the steps set out in the Procedure for connection and acceptance of Scheduling Coordinators’ information systems to the TSO’s information system (Procedura przyłączania i akceptacji systemów informatycznych OR do systemów informatycznych OSP dla WIRE/UR i WIRE).