Yearly capacities

Yearly values of cross-border transmission capacity

PSE S.A. publishes herewith values of cross-border transmission capacity which was calculated with consideration of transmission system security standards and with respect to operating procedure and planning. The publication has been prepared based on yearly transmission grid maintenance schedule.

 

  Year 2026: PL - DE/CZ/SK
(export)
[MW]
  Okres TRM NTC ZPO* AAC** Reason of Congestion (outage)***
1 01.01 - 15.02 1300 1100 0 0  
2 16.02 1300 1100 0 0 Nosovice-Wielopole
3 17.02 1300 1100 0 0  
4 18.02 1300 1000 0 0 Spisska Nova Ves-Liptovska Mara
5 19-24.02 1300 1100 0 0  
6 25.02 1300 1000 0 0 Spisska Nova Ves-Lemesany
7 26.02-02.03 1300 1100 0 0  
8 03.03-24.03 1100 0 0 0 Krosno Iskrzynia-Rzeszów, Krosno Iskrzynia-Lemesany t.1 t.2
9 25.03-31.03 1300 900 0 0 Krosno Iskrzynia-Rzeszów,
10 01.04-02.04 1600 1500 0 0 Kapusany-Mukaczewo, Krosno Iskrzynia-Rzeszów, Joachimów-Wielopole
11 03.04-06.04 1600 1500 0 0 Kapusany-Mukaczewo, Krosno Iskrzynia-Rzeszów
12 07.04-08.04 1600 1100 0 0 Kapusany-Mukaczewo, Rzeszów-Chmielnicka, Krosno Iskrzynia-Rzeszów
13 09.04-13.04 1600 1500 0 0 Kapusany-Mukaczewo, Krosno Iskrzynia-Rzeszów
14 14.04-25.04 1600 500 0 0 Kapusany-Mukaczewo, Krosno Iskrzynia-Rzeszów, Krosno Iskrzynia-Lemesany t1 t2
15 26.04-27.04 1600 1600 0 0 Kapusany-Mukaczewo, Joachimów-Wielopole
16 28.04 1600 800 0 0 Kapusany-Mukaczewo, Joachimów-Wielopole, Krosno Iskrzynia-Tarnów
17 29.04-04.05 1600 1600 0 0 Kapusany-Mukaczewo, Joachimów-Wielopole
18 05.05-06.05 1600 1100 0 0 Kapusany-Mukaczewo, Joachimów-Wielopole, Rzeszów-Chmielnicka
19 07.05-09.05 1600 1600 0 0 Kapusany-Mukaczewo, Joachimów-Wielopole
20 10.05-18.05 1600 1600 0 0 Kapusany-Mukaczewo
21 19.05-21.05 1600 1100 0 0 Kapusany-Mukaczewo, Rzeszów-Chmielnicka
22 22.05 1600 1600 0 0 Kapusany-Mukaczewo, Liskovec-Bujaków
23 23.05-31.05 1600 1600 0 0 Kapusany-Mukaczewo
24 01-02.06 1600 1700 0 0  
25 03.06 1600 1100 0 0 Rzeszów-Chmielnicka
26 04-08.06 1600 1700 0 0  
27 09.06 1600 1300 0 0 Dobrzeń-Detmarovice
28 10-13.06 1600 1700 0 0  
29 14.06 1600 1500 0 0 Krosno Iskrzynia- Rzeszów
30 15-19.06 1600 500 0 0 Krosno Iskrzynia- Rzeszów, Krosno Iskrzynia- Lemesany t1 t2
31 20.06 1600 1500 0 0 Krosno Iskrzynia- Rzeszów
32 21.06-12.07 1600 1700 0 0  
33 13-17.07 1600 1000 0 0 Nosovice-Varin
34 18-19.07 1600 1700 0 0  
35 20-24.07 1600 1100 0 0 Rzeszów-Chmielnicka
36 25-26.07 1600 1700 0 0  
37 27.07-14.08 1600 500 0 0 Krosno Iskrzynia-Lemesany t1 t2, Krosno Iskrzynia-Rzeszów
38 15-16.08 1600 1700 0 0  
39 17.08-31.08 1600 0 0 0 Wielopole-Nosovice, Albrechtice-Detmarovice, Albrechtice-Nosovice
40 01.09-06.09 1600 0 0 0 Wielopole-Nosovice, Albrechtice-Detmarovice, Albrechtice-Nosovice, Kapusany-Mukaczewo
41 07-11.09 1600 1300 0 0 Dobrzeń-Detmarovice, Kapusany-Mukaczewo
42 12.09-13.09 1600 1600 0 0 Kapusany-Mukaczewo
43 14.09-18.09 1600 1500 0 0 Kopanina-Liskovec, Kapusany-Mukaczewo
44 19.09-21.09 1600 1600 0 0 Kapusany-Mukaczewo
45 22.09 1600 1300 0 0 Dobrzeń-Detmarovice, Kapusany-Mukaczewo
46 23-24.09 1600 1100 0 0 Kapusany-Mukaczewo, Chmielnicka-Rzeszów
47 25.09-30.09 1600 1600 0 0 Kapusany-Mukaczewo, Chmielnicka-Rzeszów
48 01.10 1600 800 0 0 Kapusany-Mukaczewo, Krosno Iskrzynia-Tarnów
49 02.10-31.10 1600 1600 0 0 Kapusany-Mukaczewo
50 01.11 1300 1100 0 0  
51 02-23.11 1300 900 0 0 Albrechtice-Detmarovice, Albrechtice-Nosovice
52 24.11-01.12 1300 1100 0 0  
53 02-04.12 1300 1000 0 0 Rzeszów-Chmielnicka
54 05-31.12 1300 1100 0 0  

 

  Year 2026: DE/CZ/SK - PL
(import)
[MW]
  Okres TRM NTC ZPO* AAC** Reason of Congestion (outage)***
1 01.01-05.02 1400 1900 0 0  
2 06.02-08.02 1400 900 0 0 Krajnik-Plewiska t1 t.2
3 09-11.02 1400 900 0 0 Krajnik-Plewiska t1 t.2, Hradec-Röhrsdorf 1
4 12-13.02 1400 900 0 0 Krajnik-Plewiska t1 t.2, Hradec-Röhrsdorf 1
5 14-22.02 1400 1900 0 0  
6 23.02-09.03 1400 1800 0 0 Gorzów-Krajnik
7 10.03 1400 1900 0 0  
8 11.03 1400 1400 0 0 Mikułowa-Hagenwerder 1
9 12.03 1400 1400 0 0 Mikułowa-Hagenwerder 2
10 13.03-15.03 1400 1900 0 0  
11 16.03 1400 1600 0 0 Dunowo-Morzyczyn
12 17.03-27.03 1400 1900 0 0  
13 28.03-31.03 1400 1600 0 0 Dunowo-Morzyczyn
14 01.04 1600 1400 0 0 Dunowo-Morzyczyn, Mikułowa AT2
15 02.04-07.04 1600 1900 0 0 Dunowo-Morzyczyn
16 08-12.04 1600 2100 0 0  
17 13.04 1600 1800 0 0 Hradec-Röhrsdorf 2
18 14-16.04 1600 1600 0 0 Hradec-Röhrsdorf 2, Mikułowa AT1
19 17.04 1600 1400 0 0 Hradec-Röhrsdorf 2, Mikułowa AT1, Krajnik-Morzyczyn 400
20 18.04 1600 1400 0 0 Mikułowa AT1, Krajnik-Morzyczyn 400
21 19-30.04 1600 1700 0 0 Mikułowa AT1
22 01-10.05 1600 2100 0 0  
23 11-13.05 1600 1800 0 0 Hradec-Röhrsdorf 1
24 14-15.05 1600 1800 0 0 Hradec-Röhrsdorf 1, Mikułowa-Świebodzice t1 t2
25 16.05-01.06 1600 1900 0 0 Mikułowa-Świebodzice t1 t2
26 02-21.06 1600 2100 0 0  
27 22-26.06 1600 600 0 0 Mikułowa-Hagenwerder 1
28 27-28.06 1600 2100 0 0  
29 29.06-03.07 1600 600 0 0 Mikułowa-Hagenwerder 2
30 04.07-09.09 1600 2100 0 0  
31 10.09-08.10 1600 1600 0 0 Czarna-Mikułowa
32 09-31.10 1600 2100 0 0  
33 01.11-31.12 1400 1900 0 0  

 

 

* Volume of capacity to be allocated in yearly auction by Joint Allocation Office S.A. The volume is determined taking into account the calculated for given timeframes NTCs and the difference between surpluss of power available for TSO, and the required surplus of power to be available for TSO, which according to IRiESP equals 18% of demand to be covered by national power plants.

Regarding import, the volume is determined taking into account the calculated NTCs and the difference between negative reserve level, and the required negative reserve level.

** Transmission capacity allocated in yearly auction coordinated auction by Joint Allocation Office S.A. (values updated after the end of an allocation process).

*** Planned maintenance of transmission network elements will be updated according to daily maintenance schedules.
 

Archives

Yearly Forecast Transmission Capacity 2024
Yearly Forecast Transmission Capacity 2023
Yearly Forecast Transmission Capacity 2022
Yearly Forecast Transmission Capacity 2021
Yearly Forecast Transmission Capacity 2020
Yearly Forecast Transmission Capacity 2019
Yearly Forecast Transmission Capacity 2018
Yearly Forecast Transmission Capacity 2017
Yearly Forecast Transmission Capacity 2016
Yearly Forecast Transmission Capacity 2015
Yearly Forecast Transmission Capacity 2014
Yearly Forecast Transmission Capacity 2013
Yearly Forecast Transmission Capacity 2012
Yearly Forecast Transmission Capacity 2011
Yearly Forecast Transmission Capacity 2010
Yearly Forecast Transmission Capacity 2009
Yearly Forecast Transmission Capacity 2008
Yearly Forecast Transmission Capacity 2007
Yearly Forecast Transmission Capacity 2006